Thursday, September 27, 2007

 

Sept 27th


The pews are being being assembled today and installed tomorrow. WOW !!


Wednesday, September 26, 2007

 

Sept 26th

The Altar, Pulpit, and Choir chairs have been delivered !





Tuesday, September 25, 2007

 

Sept 24th

The welcome center has been delivered and put together - this will be our "connection point". One of the parlor rooms has been arranged with furniture and is very comfortable and inviting just as it is. The prayer / communion kneelers have been assembled and put into place on the chancel and the sanctuary floor.





Sunday, September 23, 2007

 

Sept 22nd


Some of the finishing touches are in place. The base of the front sign has been set. The lines have been painted on the parking lot. The cap for the stone work on the two posts has been done. We also had the building inspectors present on Friday and we got the go-ahead to start moving in.




Wednesday, September 19, 2007

 

Sept 19th

The cafe lighting is now in place. The carpet in the sanctuary in down and they are working on the chancel carpet now. The sanctuary wall sconces add a wonderful touch to the room.





Tuesday, September 18, 2007

 

Sept 17th

The parking lot and access roads have been paved! It looks and feels so much better as you drive in and around the parking lot.

Friday, September 14, 2007

 

Sept 14th

The foundation for the front sign is in place. The tile flooring and lighting are in place in the sanctuary. A view of Clay North from the Swanson school property line





Thursday, September 13, 2007

 

Sept 12th


Things are coming together..... The last of the hydroseeding has been done, the coverings over the lobby and the cafe floor have been removed so we can now see what it looks like.




Tuesday, September 11, 2007

 

Sept 11th

The Flooring (VCT) that will be under the pews has been started.

Monday, September 10, 2007

 

Sept 10th

Our first funiture has been delivered (and assembled). This table set is in one of the two parlor rooms that are adjacent to the cafe'.

 

Sept 7th

A view of the chancel with the light coming through the windows at the top of the cupola and shining on the cross. All the lighting is now in place and focused..... You have to see that in person to appreciate the space

Wednesday, September 05, 2007

 

Sept 5th

Much of the lighting has been hung today (left picture is on the chancel facing the congregation). We still have 32 lights waiting to be hung tomorrow. Meanwhile, the front sign foundation is being prepared.