Saturday, January 27, 2007
January 26th
The Steel is here, the steel is here ! 

There are piles steel of components all over the parking lot. Check back next week as the crews are planning to start erecting the steel on Monday and I hope to be on site each day of the week to get pictures
Sunday, January 21, 2007
January 20th
About 1/2 of the building floor has been graded and covered with insualted tarps (grey and black area in the right side of the picture) in preparation for pouring of the concrete floor. January 19th
January 17th

Here is the front of the chancel area. The lowest footing (at the top of my head in the shadow) will be the front face of the chancel.
January 13th
Time Lapse photo spot. Hard to even tell it's winter in South Bend - except for the trees and sky in the background. Most of the work the past week has continued to be underground installation of plumbing lines and electrical conduits